We're down to the final stretch! In about two weeks from today we should be receiving our keys! That's if everything goes exactly as planned...which never usually happens. The goal is to move in the last week of June, but we'll just expect that it will probably be the first week of July.
A lot of progress has been made, mostly cosmetic. The siding is FINALLY finished. There was some sort of delay getting another box of triple 3" vinyl siding to finish the left side of the house. You remember...the side that they kept borrowing from to finish the rest of the house.

And notice the a/c compressors in the above photo. There is some question as to whether these are actually the correct units. You may remember from a previous post the whole air handler mix-up. As far as I know, everything HVAC related was "fixed". There should be two 2.5 ton units inside the house: one in the crawl space, and one in the attic. It would seem to me that the a/c compressors would need to be the same size as well. Which as you can see, they are not. ??? Our superintendent is trying to get a hold of the HVAC crew to find out, once again, what happened.
Other progress includes:

All interior doors painted and hung

Newel posts installed for stair railings

Granite counter tops and bathroom counters installed

Faucets, shower heads and plumbing hooked up

Toilets & bathroom floors installed

Water heater in crawl space

Lighting fixtures hung & electricity turned on!

Dustin terminated all of his network cables and outlets and installed plates

Garage floor poured

Brick column bases for front porch


Back door re-installed...
Speaking of the back door, they originally ordered the wrong door. It swung to the outside of the house instead of in towards the wall. But they hung it anyway so the house would pass the framing inspection. Well, the siding guys finished the trim around the back door before it was replaced. We thought it would be an easy switch, but it turns out the new door and frame was slightly skinnier and taller than the other door. How do these things happen? The finish carpenter had to rip down the hardie board trim above the door (breaking it in the process) and shim the sides to get the new door frame to fit. So now we are missing a trim piece AND there are gaps on both side of the door. The siding guys are supposed to come fix it any day now.
Next on the schedule:
Finishing the front porch, including the craftsman tapered columns that I have been dying to see!
Stair railings and miscellaneous interior trim
Carpet in all the bedrooms and vinyl flooring in kitchen
Mirrors and closet shelves
Pour driveway and sidewalks
Final grade and smoothing out the dirt around the house
Some Appliances in kitchen:

Whirlpool Vented Range Hood

Whirlpool Gas Range & Double Oven

Dustin's parents are planning another trip to come and help us with some of our final projects. This weekend we are going to start building the built-in bookshelves and fireplace mantle in the living room. We will also try to get the art room painted and install the baseboards and window trim. Luckily, we get to use all of the excess molding and 1x4 trim from the rest of the house. That stuff can get pretty expensive, so we are grateful to have the left overs for our art room!
Then the weekend of the 24th will be spent installing our wood floor downstairs. That will be the final project before we can actually move anything in to the house. Of course there are plenty of other projects planned, but none that need to finished immediately. I have a feeling this house is going to be a work in progress for a long time. But I will love every minute of it!